Synergy 8024-30/8024-40 - JK Synergy Stage 4 Long Arm System User Manual

Page 14

Advertising
background image

14. INSTALL SWAY BAR LINKS

a) Install the driver side anti-way bar relocation bracket using a 1.5”spacer and ½” x

3” bolt and top-lock nut; use a washer under the bolt-head and nut.


Figure 14-1

b) Run a 1/2” drill bit or reamer through each side of the stock sway bar holes to

enlarge the holes for the new rod end studs.

Figure 14-2

c) Make sure the sway bar end links are the same length by adjusting the rod ends.
d) Install the sway bar link rod ends to the sway bar as shown in Figure 14-1, tighten

to 60 ft-lbs.

e) Install the driver side sway bar link to the sway bar relocation bracket using the

stock nut/bolt as shown in Figure 14-1. Torque the lower sway bar nut/bolts to 75
ft-lbs.

f) Install the passenger side sway bar links in the side of the track bar bracket using

the stock nut/bolt. See Figure 14-3

g) If you do not want to relocate the sway bar links to the higher hole you can install

the sway bar link in place of the spacer on the passenger side and eliminate the
relocation bracket on the driver side. Make sure that the sway bar links and sway
bar do not go past strait when the axle is at full droop and that the sway bar links
do not contact the drag link.

Advertising
This manual is related to the following products: