2 dash switches, Dash switches – JLG G12-55A Service Manual User Manual

Page 164

Advertising
background image

Electrical System

9-22

G10-55A, G12-55A

9.11.2

Dash Switches

a. Switch Removal

1. Park machine on a firm, level surface, level machine,

fully retract boom, lower boom, place transmission
control lever in (N) NEUTRAL, engage park brake
and shut engine OFF.

2. Place a Do Not Operate Tag on both ignition key

switch and steering wheel.

3. Open engine cover. Allow system fluids to cool.

4. Properly disconnect the batteries.

5. Each switch (16) is mounted in dash panel (17).

6. Pull switch out of dash panel and disconnect

harness connector to switch in question.

b. Disassembly

DO NOT disassemble dash panel switch. Replace a
defective switch with a new part.

c. Inspection and Replacement

Inspect the switch terminals for continuity and shorting in
both the engaged and disengaged positions. Replace a
defective or faulty switch with a new switch.

d. Switch Installation

1. Connect the switch to the cab harness connector.

2. Position the switch over the rectangular opening in

the dash and snap into position.

3. Properly connect the batteries.

4. Start the machine and check the replaced switch for

proper function.

5. Close and secure the engine cover.

6. Remove the Do Not Operate Tags from both the

ignition key switch and the steering wheel.

MAL1380

17

16

Advertising
This manual is related to the following products: