Xit6000-ca, Maintenance, Preventative maintenance schedule – BAND-IT XIT 6000-CA 3/8 Tie-Lok Tool User Manual

Page 22: 3/8” tie-lok, Tool

Advertising
background image

Document # XIT177 Rev E

© Copyright

BAND-IT-IDEX, Inc. 2005

All rights reserved

www.BAND-IT-IDEX.com

BAND-IT-IDEX, Inc.

A Unit of IDEX Corporation

4799 Dahlia Street Denver, CO 80216-3070 USA

P: 1-800-525-0758 F: 1-800-624-3925

22

XIT6000-CA

3/8” Tie-Lok

®

Tool

The XIT6000-CA requires preventative maintenance as indicated below. The “Clamps
Installed” column indicates how many clamps can be installed between each servicing.

Maintenance

Replace gripper

Front Gripper

50,000

Replace Assembly

Tension Block Assembly

50,000

Clean, re-lubricate, and inspect for

multiple broken teeth

Front Gripper

25,000

Rotate (page 18)

Cut-off Blade

25,000

Clean & Re-Lubricate

Tool Head

25,000

Clean & Re-Lubricate

Flip Cover

12,500

Clean & Re-Lubricate

Tension Block Assembly

12,500

Maintenance

Action

Maintenance

Item

Clamps

Installed

Replace

Cut Off Blade

50,000

Replace

Cut-off Knife Assembly

25,000

Clean & Re-Lubricate

Mechanical Linkage

25,000

Preventative Maintenance Schedule

Tool Preventative Maintenance:
The tool has some wear components that must be checked and replaced on a certain
schedule. BAND-IT has developed a Preventative Maintenance (PM) schedule to help
facilitate these requirements. An excerpt from this PM Schedule is shown below. If tools
are experiencing difficulties during function or there audible air leaks coming from inside
the handle, the tool should be returned to BAND-IT-IDEX, Inc. for servicing.

Advertising