Floor mounting, Figure 1 - bottom view floor mount dimensions, Clearance – Rockwell Automation 1608P ProDySC User Manual, 200 A User Manual

Page 8: Bypass switch, Circuit breaker recommendations, Table 1 - recommended branch circuit protection

Advertising
background image

8

Rockwell Automation Publication 1608P-UM003A-EN-P - September 2013

Chapter 2

Installation

Floor Mounting

The ProDySC is to be secured to the floor using fasteners and fittings appropriate
for the type of floor. Holes are provided in the base channels; see

Figure 1

for

mounting dimensions.

Note: Top or bottom cable entry is allowed. See

Figure 1

and

Figure 2 on page 9

.

Figure 1 - Bottom View Floor Mount Dimensions

Clearance

ProDySC doors hinge on both right and left. See

Figure 26 on page 34

for

dimensions including door swing. Leave required clearances:

Door swing must allow doors to open at least 90 degrees

12” [300mm] clearance on left side and rear for cooling airflow

4”[100mm] on right side for air filter clearance when right door opens

Bypass Switch

Installation of an external maintenance bypass switch is recommended for service
and/or maintenance. Typical switch arrangements are shown in

Figure 3 on

page 10

and

Figure 4 on page 11

. Contact Rockwell Automation for

recommendations and requirements.

Circuit Breaker
Recommendations

Branch circuit protection upstream of the ProDySC is required. Recommended
circuit breakers and maximum allowed circuit breaker ratings are listed in

Table 1

. Branch circuit protection rated less than the ProDySC current rating

may result in nuisance tripping.

Table 1 - Recommended Branch Circuit Protection

ProDySC Rating

Max. MCCB Rating

200 A

250 A

Advertising