Figure 4 - MegaDySC Cabinet Preparation for SBS Layout

Figure 5 - ER Storage Cabinet Preparation for SBS Layout

Preparing the ER System for BTB layout

1.

Remove all tan-colored masking dots, blue-colored tape, and all plastic
sheets.

2.

Remove all eight (8) plastic 13 mm hole plugs in the right side of the
switchboard cabinet.

Remove these two (2)
75mm” Dia. EKO’s

Remove plugs from
these two (2) locations

Do not remove
these two (2) plugs

Remove these two
(2)63mm Dia. EKO’s

Remove and SAVE
3/8-16 hardware from
two (2) locations