Powerup Sequence

On powerup, the module performs the following in sequence.

1. RAM test
2. Flash image verification
3. Load image from flash and execute
4. Initialize LED and display handler
5. Initialize DLR
6. Check configuration switches and initialize TCPIP
7. Initialize 1746 backplane
8. Initialize main application

a. Create CIP Objects

b. Initialize Ethernet/IP stack

c. Create I/O manager

9. Initial DUP ID (duplicate ID) check

10. Initialize Web server
11. Enable I/O and messaging

Solid green

<IP address>

Module is
communicating and
working properly.

None

None

Solid Red

“0001”

Fatal error

The adapter has
failed a hardware
test, discovered too
many I/O racks
(greater than 3), or
reached a state from
which it cannot
recover.

Verify the correct
number of I/O
racks and power
cycle the adapter.
Contact Technical
Support if
problem persists.

Four-character Status Display

MOD LED

Display

Description

Probable Cause

Recommended
Action