Start Up Preparation & Procedures

The following check list shall be adhered to before putting the compres-

sor into operation.

1. Remove all loose pieces and tools around the compressor installation.
2. Check oil level in crankcase, add as necessary.
3. Check all pressure connections for tightness and leaks.
4. Check to make sure all safety relief valves are in place and operational.
5. Check to be sure all guards are in place and securely mounted.
6. Check fuses, circuit breakers and thermal overloads for proper size.
7. Open all manual shut-off valves (block valves) at and beyond the

compressor discharge.

The following procedures should be followed for start-up of a new instal-

lation, or after changes have been made to an existing installation, and/or

after service repair work has been performed.
1. Instructions in addition to those contained within this manual, supplied

by manufacturers of supporting equipment, must also be read and

understood before start-up.

2. Check oil level in crankcase.
3. Drain moisture from air receiver and traps.
4. Start compressor and watch for excessive vibration or strange noises.

If either is observed, stop the compressor immediately and correct.

5. Check air receiver or system pressure.
6. Manually activated safety relief valves by pulling ring or lever.
7. Check operation of controls.
8. After two days of operation check belt tension, air piping for leaks, and

crankcase oil level.

CAUTION

Failure to perform the checks may result in serious injury or death,

property damage and/or mechanical failure. Disconnect and lock out

power supply.

start

up

preparations

Advertising