Section Five: Zig Zag Installation

Z17

JUNCTION
BOX

1

MOUNTING
BRACKET

PHILLIPS
SCREW

ADJUSTABLE
MOUNTING BAR

1: Mount each adjustable mounting bar to one side of the
junction box and secure them with the mounting brackets
and two Phillips screws provided.

2: Place the lips on the adjustable mounting bars against
the studs. Secure the adjustable bars to the studs with
the eight #8 screws.

3: Install conduit (if required by local electrial code) and run
low-voltage power wires to the junction box.

NOTE:

The adjustable mounting bars mount to studs that

are spaced 13" to 24" apart.

INSTALLATION

DIRECTION

ADJUSTABLE
MOUNTING BAR

STUD

#8 SCREW

2

3

JUNCTION
BOX

CONDUIT W/
LOW-VOLTAGE WIRES

7: Insert the joiner bars halfway into the channel trap door
frame. Tighten the two M4 set screws on each joiner bar
with a 1.5MM Allen wrench.

8: Slide the other section of channel onto the joining bars and
tighten the remaining M4 set screws with a 1.5MM Allen
wrench.

1: Mount each adjustable mounting bar to one side of the
junction box and secure them with the mounting brackets
and two Phillips screws provided.

6" FIXED
JAB SAW

4: Mark the area where the junction box will be located on the
drywall.

5: Install the drywall.

6: Cut out the marked areas to expose the junction box.

4

6

WALL

7

8

STARTER
SECTION

CHANNEL
SECTION

9: Assemble the lens to the channel before cutting.

LENS

CHANNEL

TRAP DOOR FRAME

10: Determine the channel length and cut channel and lens at a 45° angle from the outer corner.

11: Cut additional lens/channel assembly for the opposing 45° angle and any other corners as required for the installation.

CHANNEL

LENGTH

45°

LENS

9

10

Z18

Z19

Z20

11

Z21