Installing subsequent screw spline modules, Step 6) installing subsequent screw spline modules – EFCO 525 Series User Manual

Page 31

Advertising
background image

A. SCREW SPLINE

SECTION VIII-FRAME INSTALLATION

[FIG. 40]

[FIG. 41]

(CONT.)

PAGE 29

STEP 6) INSTALLING SUBSEQUENT SCREW SPLINE

MODULES

Make sure that the anchors are installed into the head and jamb of the

first module as specified in figures 34-37 on page 26 and 27. The 795

sealant should be applied to the mullion and to the subsill as specified in

figure 31 on page 25 and in figures 38 and 39 on page 28. Place the

second module on the subsill at an approximate 30 degree angle. Rotate

the module into the condition approximately 1/4" away from the

previously installed module. Once the second module is in place 1/4"

from the first module, slide it into position and begin snapping the mullion

halves together. When the two mullion halves are fully snapped, press

the second mullion down onto the subsill to make the sill flush with the

top of the subsill as shown in figure 32 on page 25. See figures 42 and

43 on page 30 for mullion snap fit instructions.

1/4"

525 IMPACT

DPS 1/2004

30˚