2 tie spacing and railboss mounting – Rice Lake RailBoss™ Rail Scales - Installation Manual User Manual

Page 8

Advertising
background image

4

Railboss Railroad Track Scale

Figure 2-4. Rail Cutting Complete

6. Once all cuts have been made, remove the loose rails from the area.

2.2

Tie Spacing and RailBoss Mounting

1. Use a back hoe to dig through existing ballast and remove the existing ties.

Note

Installing new ties is recommended; if existing tiles are in good condition, they will still need to be removed to
allow for alignment and spacing needs beneath the RailBoss sections.

2. Drill two standard-spaced 1.25" holes in existing rail to allow for RailBoss mounting.

Figure 2-5. Holes Drilled in Existing Rail

3. Place ties in position shown in Figure 2-6.

RailBoss

RailBoss

RailBoss

RailBoss

Existing Rail

36”

36”

Figure 2-6. Tie Spacing in Relation to Existing Rail and Installed RailBoss

4. Adjust ballast beneath ties as necessary to maintain plumb.

5. Install RailBoss sections by inserting bolts through pre-drilled holes in the RailBoss and joint bars (or

compromise bars if needed). Finger-tighten one nut on each bolt.