RECEIVING AND INSTALLATION

SECTION 1 - RECEIVING
1.1 General
Every precaution has been taken to pack the battery for shipment to ensure its safe arrival. As soon as you

receive the battery, check the packing material for evidence of damage in transit. If the packing material is

physically damaged or wet acid stains are present, make a notation on the delivery receipt before you accept the

shipment/delivery.

Note: Freight carriers generally require that concealed damage be inspected by the carriers representative within

10 days from date of delivery to determine responsibility. The resolution of such claims may extend up to

9 months. It is the receiving facility’s responsibility to notify the freight carrier of concealed damage.

Verify the number of cartons and skids against the bill of lading and verify their components against the packing

lists. Keep a copy of the verified lists for your installation records. It is important to verify that the accessory

package is present and the component quantities are correct.
Accessory kits for complete battery systems typically consist of:

Inter-cell and/or inter-unit connectors

Inter-tier (or step or row) cable connectors

Terminal plates

Connection bolts, nuts and washers

NO-OX-ID grease

Hydrometer, hydrometer holder, thermometer, labels, flame arrestor vents, and cell numbers

Lifting sling and wood spreader (when applicable for larger cell types)

Note: C&D does not furnish cross aisle connections. If the final system arrangement is different from a specific

ordered design, the quantities of the interconnection components will probably change and must be

ordered as additional, optional components.

Replacement identification labels

Note: In some cases, where batteries are shipped from stock or per customer request to a changed location,

the battery may not ship with the tracking order number on the battery identification label. In these

cases, replacement identification labels containing the correct order number will be shipped as part of

the accessory kit. Please apply these updated labels over the existing labels on the cover of the cells.

Battery racks are manufactured at a different location than the batteries and are shipped separately. Racks are

shipped unassembled and consist of:

Frames

Support rail assemblies and insulating covers

Cross braces

Restraint rails, brackets and cell spacers (seismic only)

Nuts, bolts, and washers

Rack outline drawings/installation instructions

Spill containment systems are available upon request. These may be required by local building or fire code.
1.2 Damage and shortage situations
C&D ships FOB plant (ownership passes at our dock). If shipments are damaged or if cartons or skids are

damaged or missing, a claim must be filed with the carrier. Place an immediate order for replacement with C&D

and use the replacement cost as the amount of freight damages or shortages involved.
If individual component items are missing, a shortage report should be filed immediately with C&D. Mail (express

mail recommended) or fax a copy of the VERIFIED component packing list. This verified list should show both

the name of the packer, as well as the quantities of items checked off by the receiver. Send this list to:
C&D TECHNOLOGIES, INC.: Attn.: Customer Service • 1400 Union Meeting Road • Blue Bell, PA 19422

Tel. +1-215-619-2700 ; FAX 215-619-7840

e-mail: [email protected]

RS1476/0215/CD

3

www.cdtechno.com

Advertising