6.1 Filling the Boiler System

1. Ensure the system is fully connected. Close all

bleeding devices and open make-up water valve.

Allow system to fill slowly.

2. If make-up water pump is employed, adjust

pressure switch on pumping system to provide

a minimum of 12 psi (81.8 kPa) at the highest

point in the heating loop.

3. If a water pressure regulator is provided on the

make-up water line, adjust the pressure regulator

to provide at least 12 psi (81.8 kPa) at the highest

point in the heating loop.

4. Open bleeding devices on all radiation units

at the high points in the piping throughout

the system, unless automatic air bleeders are

provided at such points.

5. Run system circulating pump for a minimum of

30 minutes with the boiler shut off.

6. Open all strainers in the circulating system,

check flow switch operation, and check for

debris. If debris is present, clean out to ensure

proper circulation.

7. Recheck all air bleeders as described in Step 4.

8. Check liquid level in expansion tank. With the

system full of water and under normal operating

pressure, the level of water in the expansion tank

should not exceed ¼ of the total, with the balance

filled with air.

9. Start up boiler according to the procedure in this

manual. Operate the entire system, including the

pump, boiler, and radiation units for one (1) hour.

10. Recheck the water level in the expansion tank. If

the water level exceeds ¼ of the volume of the

expansion tank, open the tank drain, and drain to

that level.

11. Shut down the entire system and vent all

radiation units and high points in the system

piping, as described in Step 4.

12. Close make-up water valve and check strainer in

pressure reducing valve for sediment or debris

from the make-up water line. Reopen make-up

water valve.

13. Check gauge for correct water pressure and also

check water level in the system. If the height

indicated above the boiler insures that water is at

the highest point in the circulating loop, then the

system is ready for operation.

14. Refer to local codes and the make-up water

valve manufacturer’s instructions as to whether

the make-up water valve should be left open or

closed.

15. After placing the unit in operation, the ignition

system safety shutoff device must be tested.

First, shut off the manual gas valve, and call

the unit for heat. After the pre-purge and ignitor

heat-up time, the main gas terminals will be

energized, attempting to light, for seven (7)

seconds, and then will de-energize. The unit will

attempt to light two more times, and then will go

into lockout mode. Second, turn the power off

and then on again, open the manual gas valve

and allow the unit to light. While the unit is

operating, close the manual gas valve and ensure

that power to the main gas valve has been cut.

16. Within three (3) days of start-up, recheck all air

bleeders and the expansion tank as described in

Steps 4 and 8 above.

Important: The installer is responsible for identifying

to the owner/operator the location of all emergency

shutoff devices.

WARNING

Do not use this appliance if any part has been under

water. Immediately call a qualified service technician

to inspect the appliance and to replace any part of

the control system and any gas control that may have

been under water.

AVERTISSEMENT

N’utilisez pas cet appareil si l’une de ses pièces est

passée sous l’eau. Appelez tout de suite un technicien

en entretien et en réparation pour inspection de

l’appareil et remplacement des pièces du système de

commande, et des pièces de commande du circuit

gaz, qui sont passées sous l’eau.

6.2 Operating Temperature Control

40

41

42

48

51

43

44

45

46

47

49

50

52

53

54

54

55

Control Access Panel

Note: The Dip switch panel and LED panel

can be found under the Control Access Panel after

removing the bolts.

Summary of Dip Switch Settings:

#1 Two Stage (Off) / Single Stage (On)

#2 Setpoint (Off) / Outdoor Reset (On) (Note:

Outdoor Reset is required for residential

operation)

#3 WWSD Inactive (Off) / Active 70°F (On)

#4 Boiler Maximum 210°F (Off) / 190°F (On)

#5 Pump Post Purge Inactive (Off) / Active 3