COMMISSIONING

COMMISSI ONING

Commissioning Check List

General

All equipment ordered by the customer is installed.

The mains and control wiring are complete and the main switch and circuit breaker turned ON.

All Controller functions for the appliance operate.

All electrical, pipe and drain connections are to manufacturer’s specifications and the relevant local and
national codes.

Operate the air conditioner for heating and cooling.

Bonaire Ducted Inverter Reverse Cycle System

Outdoor unit is installed away from flammable and corrosive materials and fumes (i.e. pool
chlorine/petrol etc).

The system has been leak tested and evacuated as per the installation instructions.

All installer settable functions have been adjusted and set correctly.

Indoor unit platform or suspension mounting is suitable as per the installation instructions.

Indoor unit is level.

Indoor unit drain/s have been checked and tested for flow and leaks.

Outdoor unit foundation / platform are suitable as per the installation instructions.

Outdoor unit is level.

All clearances around the outdoor unit are to the manufacturer’s specifications.

Check for abnormal noise or vibration during operation of both heating and cooling.

Check that the noise, condensate drainage or air flow does not disturb the neighbours.