Fig. 3.18 – EZ-ACCESS PATHWA MODULAR ACCESS SYSTEM User Manual

Page 20

Advertising
background image

- 20 -

3.6.

ANCHOR RAMP UPPER TRANSITION: The MRUT (RAMP UPPER TRANSITION)
must be anchored to a substantial surface. Use the pre-drilled holes at each corner of the
upper transition as guides.

3.6.1.

IF RESTING ON A WOODEN SURFACE:

3.6.1.1.

Secure upper transition by installing the 1/4

″ self-drilling stainless

steel screw through each hole (FIG. 3.18).

3.6.2.

IF RESTING ON A CONCRETE SURFACE:

3.6.2.1.

Transfer the hole locations from the upper transition to the
concrete surface, then remove the upper transition.

3.6.2.2.

Using a 1/4

″ masonry bit, drill two 1-1/2″ deep holes at the

marked locations. NOTE: After drilling, make sure that the holes
are free of any residue and/or debris.

3.6.2.3.

Re-attach the upper transition and align over the drilled holes.

3.6.2.4.

Drive the 1/4

″ diameter mushroom head pin anchors into the

holes on the upper transition with a hammer until the head is
seated.

FIG. 3.18

Advertising