Sequence of Operation

c.

Minimum Off Timer ( User Adjustable )

Once a stage has been turned off, it must remain off for this amount of
time before it can be restarted.

d.

Changeover Delay ( User Adjustable )

If the previous HVAC mode was for heating, the cooling mode is not
allowed to activate any compressors until this delay period has been
satisfied. This period is used to prevent rapid cycling back and forth
between the heating and cooling modes.

The Relay Output assignment always assigns cooling stages starting with those defined
on the TUC-5R+ board and then any additional stages defined on the Relay Expansion
board. The stages are assigned from the lowest relay number up to the highest. If you
defined 6 relays for cooling and two were on the TUC-5R+ board and the remaining four
were on the relay expansion board, then stage #1 would be the lower relay number on the
TUC board and stage #3 would be the lowest relay number on the expansion board.

NOTE: You must take into account the stage assignments

when you physically wire the controller and/or
expansion board into your AHU equipment.