Flowserve Desuperheaters User Manual

Page 16

Advertising
background image

Desuperheaters FCD VLENIM0115-00– 09/11

16

8. If large capacity nozzles are required: Obtain the new nozzles from the Flowserve factory. The

nozzles will be sized according to the new process conditions and made to fit the existing nozzle
head. Ensure that the nozzle mounting cavities are cleaned prior to installing and tightening the
nozzles with a screwdriver.

9. Install the nozzle head case onto the nozzle head face and tighten to at least 12 ft-lbs (16.2 N-m) of

torque.

10. With similar weld metal (usually 316 SS), tack weld the nozzle head case to the nozzle head face in

two locations.

11. Inspect lance for wear, leaks, or cracks. Replace or repair if necessary.

12. Install the nozzle head assembly onto the lance pipe connection with at least 1 to 3 turns beyond

finger tight.

13. With similar weld metal (usually 316 SS), tack weld the nozzle head in two locations onto the lance

pipe connection.

14. Install the desuperheater into the steam pipeline in the reverse order that it was removed.

Figure 14: Cross-section of VaporCool Lance

Cooling Water

Flange

Nozzle Head

Case

Lance Pipe

Connection

Mounting Flange

Nozzle

Nozzle Head Face

Lance