Installation, Continued), 2 – electrical operation – Emerson 7ADTB User Manual

Page 6: Transfer test

Advertising
background image

INSTALLATION

(continued)

1---4

RED

RED

GREEN

GREEN

observe

these lights

AMBER

operate

this switch

Figure 1-3. Standard controls and indicators.

2 – Electrical Operation

This procedure checks electrical operation of the ADTS.

Close enclosure door before proceeding to prevent

personal injury in case of electrical system fault.

Transfer Test

The ATS should still be bypassed. Both normal and
emergency sources must be available and the emergency
source generator (if used) must be capable of being
started; put engine starting control in automatic position.
The Transfer Switch Connected to Normal light and the
Normal Source Accepted light should be on.

1. Turn the Isolation Handle counterclockwise to the

TEST position.

NOTE:

The engine generator may be signalled to start while

turning the Isolation Handle. If emergency source is available,
the ATS may operate to the emergency position. If it does,
operate Retransfer Delay Bypass switch.

2. Perform steps 1–5 at right. Observe the status lights.

See Figure 1–3.

Black square means light is on.

White square means light is off.

3. Turn the Isolation Handle clockwise to the CONN

(connected) position.

4. Turn Bypass Handle clockwise to the OPEN position.

This completes the Functional Test of the 7ADTB.

1

Turn and hold Transfer Control

switch clockwise to Transfer

Test until the engine starts

and runs (within 15 sec.). The

Emergency Source Accepted

light should come on.

Load

Disconnect

Active

2

Transfer switch CN opens and

the Transfer Switch Connected

to Normal light should go off

and the Load Disconnect Active

light should come on. Both CN

& CE contacts are now open.

Load

Disconnect

Active

3

After the delay transition time

delay, the CE Transfer switch

will operate to the Emergency

position. The Transfer Switch

Connected To Emergency light

should come on and Load Dis-

connect Active light goes off.

Load

Disconnect

Active

4

Transfer switch will operate

back to Normal position after

Feature 3A time delay. For im-

mediate retransfer turn Transfer

Control counterclockwise to

Retransfer Delay Bypass. The

Transfer Switch Connected To

Normal light should come on;

Transfer Switch Connected to

Emergency light should go off.

Load

Disconnect

Active

5

The engine–generator will stop

after the Feature 2E time delay

(unloaded running engine cool-

down). The Emergency Source

Accepted light should go off.

Load

Disconnect

Active