Figure 15 hard pipe connection diagram, 1 leak-checking and evacuation, 2 header system – Emerson Liebert XDR User Manual

Page 23: Leak-checking and evacuation, Header system

Advertising
background image

Piping

17

Figure 15 Hard pipe connection diagram

6.6.1 Leak-Checking and Evacuation

Refer to the Liebert XDC or Liebert XDP user manual for procedures for evacuation, leak check,

charging and startup.

6.6.2 Header System

The Liebert XDR module system with optional flexible piping requires use of the Liebert XD prefabri-

cated piping assembly. The prefabricated piping is compatible with the Liebert XD Flex Pipe required

to attach to the Liebert XDR modules. For the details on piping connection locations, see Figure 14.
For additional information, refer to the Liebert X-treme Density System Design Manual, SL-16655,

available at the Liebert Web site:

www.liebert.com

Top of

Liebert XDR

and

Equipment

Rack

Return Main
(seen from end )
2-1/8" O.D.
or 2-5/8" O.D.

Recommended Arc

Acceptable
Arc

Copper Tubing
Total length of each line
from Liebert XDR to
Main not to exceed 72"
(1829 mm)

7/8” Refrigerant -Grade
Full-Port Ball Valve
Field-Supplied and
Field-Installed

Return from
Cooling Module

Supply Main
(seen from end )
1-1/8" O.D.
or 1-3/8" O.D.

1/2” Refrigerant -Grade
Full-Port Ball Valve
Field-Supplied and
Field- Installed

Supply
to Cooling
Module

Rear of

Equipment Rack

Refer to Table 1 for details.