INSTALLATION

(continued)

1---4

RED

RED

GREEN

GREEN

observe

these lights

operate

this switch

Figure 1-5. Standard controls and indicators.

3 – Electrical Operation

This procedure will check the electrical operation of the
Automatic Transfer Switch. See Figure 1–5.

Be sure to close the enclosure door before

proceeding to prevent personal injury in case

of electrical system fault.

Transfer Test

Both normal and emergency sources must be available
and the emergency source generator (if used) must be
capable of being started in this procedure.

Perform steps 1 through 5 at the right. Observe the
status lights.

Q

Black square means light is on.

S

White square means light is off.

This completes the Functional Test of the ATS.

1

The Transfer Switch Connected

To Normal and Normal Source

Accepted lights should be on.

2

Turn and hold Transfer Control

switch clockwise to Transfer

Test until the engine starts

and runs (within 15 sec.).

Emergency Source Accepted

light should come on.

3

Transfer switch will operate to

the Emergency position after

Feature 2B time delay. The

Transfer Switch Connected To

Emergency light should come

on and Load Connected to Nor-

mal light goes off.

4

Transfer switch will operate

back to Normal position after

Feature 3A time delay. For im-

mediate retransfer turn Transfer

Control counterclockwise to

Retransfer Delay Bypass. The

Transfer Switch Connected To

Normal light should come on;

Transfer Switch Connected to

Emergency light should go off.

5

The engine–generator will stop

after the Feature 2E time delay

(unloaded running engine cool-

down). The Emergency Source

Accepted light should go off.