Testing & service, Continued), Table 2-1. trouble-shooting checks – Emerson ASCO 7000 User Manual

Page 8

Advertising
background image

TESTING & SERVICE

(continued)

2---2

MANUAL LOAD TRANSFER

This procedure will manually transfer the load if the

controller is disconnected.

Do not manually operate the transfer switch

until both power sources are disconnected

(all conductors deenergized).

1. Deenergize both the normal and emergency source

conductors (remove fuses or open circuit break-

ers).

2. Use the maintenance handle to manually operate

the transfer switch to the opposite source. See

Manual Operation on page 1–2.

3. If the transfer switch is in the Emergency position

manually start the engine generator and then

install emergency source fuse or close the circuit

breaker.

TROUBLE-SHOOTING

Note any optional accessories that may be furnished on

the automatic transfer switch (ATS) and review their

operation. Refer to any separate drawings and/or

instructions that may be packed with the ATS.

Hazardous voltage capable of causing shock,

burns, or death is used in this switch.

Do not touch the power or load terminals

of the transfer switch!

Table 2-1. Trouble-Shooting Checks.

CHECK IN NUMERICAL SEQUENCE

PROBLEM

1

OPERATION

2

GEN-SET

3

VOLTAGE

Engine–generator set does

not start when the Transfer

Control switch is turned and

held in Transfer Test position

or when the normal source

fails.

Hold Transfer Test switch 15

seconds or the outage must

be long enough to allow for

Feature 1C time delay plus

engine cranking and starting

time.

Starting control must be in the

automatic position. Batteries

must be charged and

connected. Check wiring to

engine starting contacts on

customer terminal block TB.

Verify that the small plug J3 is

connected to receptacle P3.

Transfer switch does not

transfer the load to the

emergency source after the

engine–generator set starts.

Wait for Feature 2B time delay

to time out (if used).

Generator output circuit

breaker must be closed.

Generator frequency must be

at least 95% of nominal
(57 Hz for a 60 Hz system.) *

Voltmeter should read at least

90% of nominal phase to

phase voltage between

transfer switch terminals EA

and EC (or EL1 and EL2 for 2

pole switches). *

Transfer switch does not

transfer the load to normal

source when normal returns

or when the Transfer Control

switch is released.

Wait for Feature 3A time delay

to time out (if used).

Voltmeter should read at least

90% of nominal phase to

phase voltage between

transfer switch terminals NB

and NC, NC and NA, and NA

and NB (or NL1 and NL2 for 2

pole switches).

Engine–generator-set does

not stop after load retransfer

to the normal source.

Wait for Feature 2E time delay

to time out (if used).

Starting control must be in the

automatic position.

* These are factory settings. Refer to the Group 5 Controller User’s Guide.

If the problem is isolated to circuits on the controller or the transfer switch, call your local ASCO Power Technologies