NSTALLATION

:

1. Check the instructions for required clearances (air spaces) to combustibles when passing through

ceilings, walls, roofs, enclosures, attic rafters, or other nearby combustible surfaces. Do not pack air

spaces with insulation.

Figure 29: Wall Framing for 10” (25.4 cm) x 10” (25.4

cm) Hole for Vertical Installation.

2. Set the gas appliance in the desired location.

Drop a plumb bob down from the ceiling to the

position of the appliance flue exit, and mark

the location where the vent will penetrate the

ceiling. Drill a small hole at this point. Next, drop

a plumb bob from the roof to the hole previously

drilled in the ceiling, mark the spot where the

vent will penetrate the roof. Determine if ceiling

joists, roof rafters, or other framing will obstruct

the venting system. You may wish to relocate

the appliance, or to offset, to avoid cutting load

bearing members.

3. To install the Round Support Box/Wall Thimble

in a flat ceiling, cut a 10 inch (25.4 cm) square

hole in the ceiling, centered in the hole drilled in

Step 2. Frame the hole as shown in Figure 29.

4. Assemble the desired lengths of black pipe and

elbows necessary to reach from the appliance

Vertical

Termination

Storm Collar

Flashing

Roofing nails

Elbow Strap

the roof line. Galvanized pipe

and elbows may be utilized in

the attic, as well as above the

roof line. The galvanized finish

is desirable above the roof line,

due to the higher corrosion

resistance.

6. Once the pipe sections have

been joined, and run up through

the hole in the roof, slip an

elbow strap over the exposed

sections, bend the support

straps outwards, and push the

elbow strap down to the roof

level, as shown in Figure 30.

Tighten the clamp around the

pipe section. Use a level to make

sure the pipe is truly vertical.

With roofing nails, secure the

adapter up through the Round Support Box. Insure that all pipe and elbow connections are in their

fully twist-locked position.

5. Cut hole in the roof centered on the small hole placed in the roof from Step 2. The hole should be of

sufficient size to meet minimum requirements for Clearance to Combustibles, as specified. Continue

to assemble lengths of pipe and elbows necessary to reach from the ceiling support box up through