30

Figure 8.9 Ceiling/Attic Construction

H. Complete Installation

WARNING! Risk of Fire! You MUST maintain 2 in.
(51 mm) air space to insulation and other combustible
materials around the chimney system. Failure to do so
could cause overheating and fi re.

• Keep chimney sections from separating or twisting.
• You may secure straight chimney sections at the joints

with screws no longer than 1/2 in. (13 mm).

The following steps should be skipped if using a

chase.

• Install

roof

fl ashing appropriate to roof pitch.

• Install round termination cap and storm collar.

I. Install Flashing

• Assemble chimney so it passes through the framed

opening.

• Slip

the

fl ashing over the chimney.

NOTICE:

Roofi ng shingles must be below the fl ashing

plate on the lower side of a sloped roof and over the
fl ashing plate on the sides and top.

• Nail

the

fl ashing to the roof. Keep gaps between the

fl ashing plate and the roof to a minimum.

• Caulk

the

fl ashing plate and roof junction as well as the

vertical seam on the fl ashing. All nail heads must be
caulked with a roofi ng sealant.

Heat & Glo • HST-42D • 27177 • Rev AB • 11/08

G. Cut out Hole in Roof

• Refer to Figure 8.9.
• Plumb from roof to center of chimney.
• Drive a nail up through roof to mark center of pipe.
• Measure to either side of nail and mark the 14-1/2 in. x

14-1/2 in. (368 mm x 368 mm) opening required.

• Measure opening on the horizontal; actual length may

be larger depending on roof pitch.

• Cut out and frame opening.
• Refer

to

Chapter 25 of the Uniform Building Code for

roof framing details.