Preparing for Operation

Instrument Preparation

2

2-21

Front Panel Operating Procedures

2-25.

Power-On Options

2-26.

There are three power-on options as listed below:

Normal Power-On Turn power switch on. The instrument communication
parameters are the same as when the instrument was last turned off.

Configuration-Reset Power-On Hold the front panel COMM key down,
and then turn the power switch on. Continue holding the COMM key until the
instrument beeps. The communication parameters are reset to default values
(see Table 2-3).

Display-Hold Power-On Hold the front panel arrow-left ( < ) key down, and
then turn the power switch on. Continue holding the < key until the instrument
beeps. The instrument front panel display remains on until you press any front
panel key. This allows inspection of the display segments.

Each power-on sequence includes a four-second self-test routine. If the self-test
fails, the instrument displays ERROR in the primary display with a code character
in the secondary display. See Chapter 6 "Maintenance" for information on error
codes. Power-on also clears channel configuration data and sets all channels to
OFF.

Table 2-3. Instrument Default Parameters

Parameter

Default Setting

Base Channel Number

1

Line Frequency

60 Hz

Network Selection

Isolated Network

Socket Port

4369

Internet Protocol Address

---.---.---.--- (dashes)

Baud Rate

19200

Default Gateway

OFF