Installation, Install ductwork, Complete installation – Greenheck Fan Make-Up Air Unit VSU User Manual

Page 4: Continued

Advertising
background image

4

Model VSU Make-Up Air

®

®

®

®

®

2. Burner/Blower Section

Use a crane and a spreader bar hooked to the factory
lifting lugs (shown below)

to lift and center the unit

onto the filter stand section. The sections can be
caulked together, but it is not needed with the water
kickouts provided with this section.

3. Install Ductwork

This table shows the duct sizes and straight lengths
recommended for optimal performance (AMCA
Publication 201-90). Using duct sizes less than
recommended will affect fan performance. Good
duct installation practices should be followed for
the remaining ductwork. See the drawings in the
Dimensional Data section for duct locations.

Recommended Supply Ductwork Sizes

VSU

Blower Size

Duct

Size

Straight Duct

Length

220

68 x 26 inches

117 inches

Installation

continued

4. Complete Installation

A typical horizontal discharge installation is shown.
Gas and/or electrical lines can be connected at this
time.
For upblast units, a duct elbow may be needed to
turn the ductwork into the building. Follow proper
ductwork methods recommended by AMCA to make
this elbow to minimize duct losses.