MODEL RATING PLATE

FLOOR DRAIN

DISCHARGE PIPE

(Do not cap or

plug)

6

AIR GAP

HOT

14

COLD

TEMPERATURE-

PRESSURE

RELIEF VALVE

CONDUIT

HOT

COLD

Installation Checklist

1. Whether or not the element conversion is made, the model

rating plate must be marked. Using a hard point ink pen,
check the appropriate block within the model rating plate,
which is located adjacent to the lower access panel.

2. Is the fuse or circuit breaker size correct as shown in the

chart in the “Product Specifications” section?

3. Are the wires from the circuit breaker or fuse service to the

water heater’s junction box on the correct wire size (gauge) as
shown in the chart in the “Product Specifications” section?

4. Is the new temperature-pressure relief valve properly

installed, and piped to an adequate drain? See
“Temperature-Pressure Relief Valve” in the “Instructions
for Installation” section.

5. Is the water heater completely filled with water? See

“Filling the Water Heater” instructions in the “Instructions
for Installation” section.

6. Will a water leak damage anything? See “Locating the

New Water Heater” in the “Instructions for Installation”
section.

7. Are the cold and hot water lines connected to the water

heater correctly? See “Water Piping” instructions in the
“Instructions for Installation” section.

8. Is there adequate clearance for maintenance around the

water heater?

9. Do you need to call your electric company to check your

wiring?