Receiving Tower

Prior to unloading the tower from the delivering carrier, inspect the shipment
for evidence of damage in transit. If damage is apparent, note the freight
bill accordingly. This will support your future recovery claim.
Find and remove the installation instruction drawings and bills of material
located in a plastic container in the cold water basin. This information should
be kept for future reference and maintenance purposes.

Hoisting Tower

All models consist of two modules per cell. Both modules have hoisting
clips. Detailed hoisting drawing are included in the literature package.

MD upper and lower modules must be hoisted and set separately. Do
not preassemble modules prior to hoisting.

A Hoisting-Installation label which has hoisting dimensional information
is located on the side casing of the tower modules. Remove tower from the
carrier and hoist into place according to the instructions on the label.

Hoisting clips are provided for ease of unloading and positioning
tower. For overhead lifts or where additional safety is required, safety
slings should also be placed under the tower. Under no circumstances
should you combine the top and bottom modules of modular models
and attempt to hoist them at the same time by utilizing the hoisting
clips alone!

Warning

Receiving and Hoisting