Cable installation, Wiring preparation, Power cable installation – Liebert UPStation GXT User Manual

Page 10: Able, Nstallation, Iring, Reparation, Ower, Caution

Advertising
background image

6

CABLE INSTALLATION

W

IRING

P

REPARATION

For access to terminal blocks, see diagrams on
page 4.

P

OWER

C

ABLE

I

NSTALLATION

Refer to the chart below when selecting cables:

!

CAUTION

Please read this section

thoroughly before attempting to

install wiring to this unit.
Be sure that the unit is not

connected to any AC mains power

source or UPS before installing

any wiring to this unit. This should

be installed by a qualified/certified

electrician.

NOTE
The 120V loads need to be balanced on

the UPS output. To do this, when

connecting 120V equipment to the

Maintenance Bypass, start at one end of

the output modules and fill in toward the

other end. Load balancing must be

performed with the UPStation

GXT6000T - 208X and 240X. It is not

required on the GXT6000T-208 because

the unit has no 120V output.

Power Cable and Protection Ratings

208V

240V

Max Input Current

30 A

30 A

Input Protection

40 A

40 A

Max Output Current

30 A

30 A

Terminal Block Details

Max: 16 mm

2

(6 AWG)

Min: 2.5 mm

2

(14 AWG)

Torque: 2 Nm (16 in/lb)

NOTE
Customer must supply power cables

between Maintenance Bypass and UPS,

utility and load. (GMB12 models are

supplied with an attached input power

cord complete with L14-30 plug.)