12. Connect the light cord ground wire (green) to the LOAD CENTER

GROUND bus.

13. Seal the cord grip using a polyurethane insulating foam sealant

(such as Great Stuff

®

) at the cord grip cap, where the light cord

exits, to restrict circulation of air flow through the conduit and cord
grip.

Note: The approved "duct seal type/method" is determined/

controlled by the local authority jurisdiction (NEC article 680.24).

14. Conduit Connection: Insert the brass conduit into the bushing thread.

Use a pipe wrench to tighten the conduit in place.

15. The Light Direct Connect installation is complete.

GROUND LIGHT WIRE
(GREEN) TO LOAD
CENTER GROUND
BUS

LIGHT POWER

CORD WIRES

RED BRASS
CONDUIT

Note: The load center
must be connected to a 25
AMP (maximum) circuit
breaker when Light Direct
Connect is installed.

SEAL CORD GRIP AT

TOP OF CAP USING

POLYURETHANE

INSULATING FOAM

SEALANT