Light Direct Connect Fitting Installation Guide

7

8.

Insert the LIGHT CORD and the COPPER BONDING GROUND
WIRE into the CORD GRIP.

9.

Slide (or twist) the CORD GRIP down to the bushing. Leave a short
length of copper bonding ground wire, enough to secure it to the
ground terminal screw.

10. Screw the CORD GRIP into the BUSHING thread. Hand tighten the

cord grip to secure the cord in place. If needed, adjust the cord grip
nut to allow the cord grip more thread into the hub.

11. Insert the 16 AWG light cord and copper bonding ground wire into

the CORD GRIP CAP. Slide the cap down to the top of the CORD
GRIP.

12. Using a torque wrench, tighten the cap onto the cord grip to a torque

value of 80 in-lbs (minimum).