Light Direct Connect Fitting Installation Guide

4

Installation for IntelliTouch and EasyTouch Load Center

The following describes how to install the Light Direct Connect in the
IntelliTouch load and power center and EasyTouch load center.

Note: For

SunTouch power center installation, see page 5.

1.

Unlatch the two load center door spring latches, and open the front
door.

2.

Remove the two retaining screws securing the high voltage
cover-panel. Remove the panel from the load center.

3.

Proceed to “Installing the Light Direct Connect Fitting Using
Non-Metallic (PVC) Conduit” (page 6), or “Red Brass Conduit”
for
installation instructions” (page 9).

4.

After the Light Direct Connect installation has been completed,
install the load center front panel and secure it with the two
retaining screws.

5.

Close the load center front door. Fasten the two spring latches. The
Light Direct Connect installation is complete.

Panel retaining screw

(Cover-panel not shown)

IntelliTouch Load Center

¾" conduit
knockout

EasyTouch Load Center

¾" conduit knockout

Panel retaining screw
(Cover-panel not shown)

CAUTION: THE
LIGHT DIRECT
CONNECT FITTING
MUST BE INSTALLED
ON THE BOTTOM OF
THE LOAD CENTER
AND ORIENTATED
DOWNWARDS ONLY.

T

GROUND BUS BAR
(for green light wire)

25 AMP Circuit Breaker
maximum

Note: Each light circuit
must be connected to a
25 AMP (maximum) circuit
breaker in the load center,
when the Light Direct
Connect is installed.