13. Connecting the Copper Bonding Ground Wire: Insert the COPPER

BONDING GROUND WIRE into the BONDING TERMINAL. Using a
torque wrench, tighten the bonding terminal screw to a torque value of
25 in-lbs (minimum).

14. Connect the light cord ground wire (green) to the LOAD CENTER

GROUND bus.

15. Seal the cord grip using a polyurethane insulating foam sealant

(such as Great Stuff

®

) at the cord grip cap, where the light cord

exits, to restrict circulation of air flow through the conduit and cord
grip.

Note: The approved "duct seal type/method" is determined/

controlled by the local authority jurisdiction (NEC article 680.24).

16. Conduit Connection: Insert and glue the PVC conduit into the UL

Listed PVC union fitting. The PVC conduit connection must be sealed
with the proper solvent cement.

17. The Light Direct Connect installation is complete.

GROUND LIGHT WIRE
(GREEN) TO LOAD
CENTER GROUND BUS

LIGHT POWER

CORD WIRES

COPPER
BONDING
GROUND WIRE

BONDING TERMINAL
SCREW

1/2” to 3/4” PVC

UNION FITTING

PVC CONDUIT
(Seal joint with sealant )

Note: Each light circuit
must be connected to a
25 AMP (maximum) circuit
breaker in the load center,
when the Light Direct
Connect is installed.

SEAL CORD GRIP AT

TOP OF CAP USING

POLYURETHANE

INSULATING FOAM

SEALANT

CORD GRIP CAP

BONDING TERMINAL

Advertising