Installation

Install the GPIB-BUF according to the following procedure.

1.

Inspect the GPIB-BUF.

2.

Verify the voltage requirement.

3.

Configure th e operating parameters.

4.

Connect the cables.

5.

Power on the unit.

These steps are described in more detail in the following subsections.

Step 1. Inspect the GPIB-BUF

Before you install the GPIB-BUF, inspect the shipping container and its
contents for damage. If damage appears to have been caused in shipment,
file a claim with the carrier. Retain the packing material for possible
inspection and/or reshipment.

If the equipment appears to be damaged, do not attempt to operate it.
Contact National Instruments for instructions.

Step 2. Verify the Voltage Requirement

The GPIB-BUF is shipped from the factory with either a 115 V or 230 V
wall-mount power supply.

Verify that the voltage on the power supply matches the voltage that is
supplied in your area.

Warning:

Operating the unit at any voltage other than the one specified
could damage the unit.