Inspection and test procedures, A. checklist, Table 5 elt inspection and test checklist – ACR&Artex B406-4 User Manual

Page 38

Advertising
background image

ACR ELECTRONICS, INC / ARTEX PRODUCTS

DESCRIPTION, OPERATION, INSTALLATION AND MAINTENANCE MANUAL

B406-4 (453-5004)

25-62-03

Page 38 of 87

JUN 20/13

TASK 25-62-03-750-802

2. Inspection and Test Procedures

SUBTASK 25-62-03-990-001

A. Checklist

(1)

Table 5 provides a list of the ELT inspection and testing requirements, a copy of which may be

used as a checklist to verify inspection and test completion. The item numbers in the table

correspond to the item identifiers for each task.

NOTE: Items 5a through 5h are mandatory requirements only in Canada, in addition to

meeting the other inspection and test requirements listed in Table 5.

Table 5 ELT Inspection and Test Checklist

ITEM NO.

DESCRIPTION

BY

1

Coax Cable and Wiring Connections Inspection

2

ELT Mounting Tray and Hardware Inspection

3

ELT Battery Pack Inspection

4

G-Switch Functional Check

5a

121.5 MHz Frequency Measurement

5b

Audio Modulation Check

5c

121.5/243.0 MHz Power Output Measurement

5d

406 MHz Frequency Measurement

5e

406 MHz Power Output Measurement

5f

Current Draw Test

5g

Digital Message Verification

5h

ELT Reset Check

6

Installed Transmitter Test

7

Antenna Test

8

Inspection and Test Documentation