Turbocharger installation, Big hoss installation 13 – Banks Power Dodge Trucks: (Diesel ’98 - 02 5.9L Cummins ISB) Tuner- Big Hoss Diesel Tuner (connects to pump wire) User Manual

Page 12

Advertising
background image

12

96759 v.4.0

TURBOCHARGER

INSTALLATION

Install the new turbine inlet gasket

provided and apply a dab of anti-seize

compound to the four turbo mounting

studs. Install the turbo-charger on the

exhaust manifold. As the turbocharger

is reinstalled, slip the oil drain tube

into the drain hose. Tighten the

turbocharger mounting nuts to 24

ft-lbs. Tighten the oil drain hose clamp.

12.

Reconnect and tighten the turbo

oil supply hose. Bolt the turbine outlet

pipe to the turbine outlet using the

original bolts.

BIG HOSS INSTALLATION
13.

For automatic transmission

models, locate and remove the rubber

plug mounted in the firewall slightly

above and to the right of the steering

shaft, as viewed facing the firewall

through the engine compartment.

Make a cross-shaped incision in the

plug and reinstall it in the firewall. See

Figure 4.
For manual transmission models, make

an incision in the main wiring loom

grommet above the wire bundle. Take

care to not cut any wiring. See Figure

4.

Figure 4

Advertising