Page 10: Proper installation of the ground rod

Advertising
background image

10

PNEG-823 Deluxe Downwind Heater

3. Heater Installation

Machine to Earth Ground

It is very important that a machine to earth ground rod be installed at the fan. This is true even if there is
a ground at the pole 15' away. This ground needs to be as close to the fan as possible, but no more than
8' away. The ground rod should be connected to the fan control panel with at least a #6 solid bare copper
ground wire, or in accordance with local requirements. The machine to earth ground provides additional
safety if there is a short. It also provides the grounding necessary for long life and operation of the solid
state circuit boards used on control circuits and the electronic ignition systems.

Figure 3A

Dig a hole large enough to hold one (1) or two (2) gallons of water. Work the ground rod into the
earth until it is completely in the ground.

Proper Installation of the Ground Rod

(Ground rods and wires are not supplied by Airstream). It is recommended that the rod not be driven into
dry ground. The following steps ensure proper ground rod installation:

1. Dig a hole large enough to hold one (1) to two (2) gallons of water.

2. Fill hole with water.

3. Insert rod through water and jab it into the ground.

4. Continue jabbing the rod up and down, the water will work its way down the hole, making it possible

to work the rod completely into the ground. This method of installing the rod gives a good
conductive bond with the surrounding soil.