Series 2 Chain Conveyors

Receiving Inspection

Carefully inspect the shipment as soon as it is received.
Verify that the quantity of parts or packages actually
received corresponds to the quantity shown on the pack-
ing slip. Any discrepancies should be clarified immedi-
ately. Please remember that any damage or missing
parts must be noted on the bill of lading at the time of
delivery. Report any damage or shortage to the deliv-
ering carrier as soon as possible. GSI’s responsibility
for damage to the equipment ends with acceptance by
the delivering carrier.

Save all paperwork and documentation furnished with
any of the enmasse conveyor components.

Pre-Installation Preparation

Familiarize yourself thoroughly with this manual and all
the conveyor parts. Read the operators manual and all
safety signs before using or servicing equipment. Tak-
ing the time to do so will aid in the assembly of your
conveyor.

Remove any banding and crating material. Arrange all
the conveyor components in such a fashion that all are
easily accessible.

Locate sturdy items to serve as blocking (i.e. wood
blocks, saw horses, etc.). Blocking is used to sup-
port the conveyor sections above the ground to help
in assembly. Locate and place the conveyor sec-
tions on the blocking in order, starting with the head
section and concluding with the tail section.