Wall bracket, Make sure th, Installation – Grain Systems Bin Accessories PNEG-1614 User Manual

Page 18

Advertising
background image

2. Installation

18

PNEG-1614 Heavy Duty Bin Stairs and Platform Assembly for 2.66" Corrugated Bin

Figure 2T Handrail Post Connection to Horizontal Wall Bracket

2. Begin installation with the upper handrail. The handrail for the first two (2) steps should be loosely

bolted to the first post and checked to ensure it is the right length. Excess length of the narrow end
of the handrail may need to be cut off and a new hole drilled for connection to the top platform
handrail. Use 5/16" x 1-1/4" bolts at the connections. Continue down the stairs installing handrail
sections to the handrail posts. Extra force maybe needed to curve the handrail on smaller diameters.
Refer to

Figure 2U

and

Figure 2V

below for connections.

Figure 2U Upper Handrail Connection

Figure 2V Upper Handrail Connection

Handrail post
(LDR-4085)

Two (2) 3/8" x 1" Flange
head bolts and nuts

5/16" x 1-1/4"
Bolt and nut

Four (4) step
handrail (STR1077)

5/16" x 1-1/4"
Bolt and nut

Advertising