Grain Systems Bin Accessories PNEG-1614 User Manual

Page 20

Advertising
background image

2. Installation

20

PNEG-1614 Heavy Duty Bin Stairs and Platform Assembly for 2.66" Corrugated Bin

Assembling Intermediate Platform (Optional Package #STR1143)

1. The intermediate platform wall brackets and bordering stair section wall brackets should be arranged

as shown

in Figure 2X

. The first platform bracket should be placed three (3) bolt spaces around the

bin and 32" below the previous stair wall bracket. The next platform bracket should be placed six (6)
bolt spaces around the bin at the same height as the previous platform bracket. The next stair wall
bracket is placed four (4) bolt spaces around the bin and 32" below the second platform wall bracket.
In each instance, the wall brackets should be attached to the bin with three (3) bolts. One hole will
have to be drilled in the bin sidewall at the third bolt’s location.

Figure 2X

2.

Figure 2Y

shows the assembly of the platform supports. Use 5/16" hardware at all the connection

points. Note the center floor brace (LS-6701) is offset from the center of the platform. (The bin wall
is hidden for clarity.)

Figure 2Y