1installation – Factory Direct Hardware Von Duprin 22EOF4 User Manual
Page 4
Advertising

911333_00(9) Page 4 of 12
RHR shown
LHR opposite
39-13/16”
to finished
floor
L
C
1.1. Mark centerline C location as shown in Figure 1-1.
1.2. For 299 or 299F strike: Tape strike template to frame
aligned with center line C as shown in Figure 1-2.
Mark and prepare mounting holes per template.
For 1409/1439 strike: Prepare frame as shown in Figure 1-3.
L
L
Figure 1-1
For double door, mullion is
already prepared for 499F strike.
Skip this step and go to Step #2.
NOTE
!
L
C
Figure 1-2. 299 or 299F Strike
Figure 1-3. 1409/1439 Strike
Template
For single door, prepare frame for 299, 299F, 1409/1439 strike.
1
INSTALLATION
7/8”
7/16”
7/16”
1-9/16” to
face of
door
Blade stop
7/8”
Cut -out
#25 Drill
#10-24 tap
1/8” Drill pilot
1” deep
Metal
W
ood
L
C
L
C