APPENDIX I

FIELD SERVICE

INSTALLATION AND STARTUP CHECKLIST

Part 3:

Starting Unit

__________ 1)

After all checks in Parts 1 and 2 are completed, conduct a startup meeting with customer to discuss the
actual procedures they might require during startup and commissioning. Also, verify with the customer that
their ‘system’ is ready for pumpage.

__________ 2)

When the system is ready, push the start button and adjust the discharge valve to meet the design point

(if required).

__________ 3)

Watch for signs of trouble (look and listen). Again, the unit must run at least ten minutes to flush out the
pump and system.

__________ 4)

Verify that the unit runs smoothly with no unusual noise, vibration, or over heating.

__________ 5)

Run the unit for one hour mechanical test (if possible).

Part 4:

Readings and Notes

A) Readings

Impeller Lift: ____________________ Shaft Runout: _____________________

Megger: __________________________________________________________

Vibration: _________________________________________________________

B) Notes:

__________________________________________________________________

__________________________________________________________________

__________________________________________________________________

__________________________________________________________________

__________________________________________________________________

__________________________________________________________________

__________________________________________________________________

_________________________________________________ ___________________
A-C Fire Pump Representative

Date

Advertising