INSTALLATION STEPS

Step 1.

FOR YOUR SAFETY turn off electrical

power supply at the service entrance before connecting

or disconnecting any wiring to the pump to avoid any

possible electrical shock hazard.

Step 2. Drain the holding tank. Also disconnect the drive
pipe and the suction pipe, the service line, and if necessary,
the volume control line. Remove old pump.

Step 3. Place the jet pump on a level, solid foundation. If
you are also replacing the existing pressure tank, refer to
Section 7 in this manual.

Step 4. Connect the drive pipe and suction pipe, the service
line and, if necessary, the air volume control line. Use either
non-toxic pipe sealing compound or tape on male thread
joints of galvanized pipe (tape or cement on plastic pipe) to
facilitate making air tight joints.

Step 5. Wire the motor.

The Red Jacket convertible jet pump is wired to the pressure
switch. The pressure switch must be grounded in compliance
with the National Electrical Code and state and local codes
and ordinances. It is mandatory that a ground connection be
made using a conductor or appropriate metal underground
water pipe or a ground lead in the service panel.

When installing a pump with a 3-prong

grounding plug do not remove round grounding prong

since it must be plugged into a grounded receptacle to

assure proper grounding.

Direct wiring instructions can be found on the inside cover of
your pressure switch.

Step 6. Prime the Pump

A. Remove the manual regulator.
B. Pour water into the pump case until it flows freely out

of the priming hole without air bubbles.

C. Turn the regulator adjusting screw counter-clockwise

until stem travel stops, or regulator poppet is near
valve bushing end. Replace regulator.

D. Turn the adjusting screw in a clockwise direction until

it is all the way in.

E. Open faucets on the downstream side of the pressure

tank to bleed off air.

F. Turn power on. Start pump. The pump should start

showing pressure on the pressure gauge.

G. To adjust the regulator, slowly turn the adjusting screw

in a counter-clockwise direction until the pressure
gauge fluctuates rapidly or the pump becomes noisy.
At this point, turn the screw clockwise until gauge
pressure holds steady.

H. Close all faucets on the downstream side. Sufficient

pressure should build up and shut the pump off.

DEEP WELL JET PUMP SYSTEM LAYOUTS

PRESSURE GAUGE

DRIVE PIPE

MANUAL REGULATOR

SUCTION PIPE

AIR VOLUME CONTROL LINE

SERVICE LINE

"T" MANUAL REGU-

LATING VALVE

DRIVE PIPE

SUCTION PIPE

PRIME HERE

SERVICE LINE

AIR CHARGING
VALVE

MANUAL REGULATOR

AIR VOLUME
CONTROL LINE

MANUAL REGULATOR

DRIVE PIPE

PRIME HERE

SUCTION PIPE

SERVICE LINE

SERVICE LINE

ISOLATOR
HOSE

PRIME HERE

"T" MANUAL
REGULATING
VALVE

DRIVE PIPE

WARNING

WARNING

FIGURE 10

SUCTION PIPE

Advertising