INSTALLATION REQUIREMENTS:

Be certain that three phase current is available at

the point of installation (see TECHNICAL DATA

for information concerning required pre-fusing of

the electrical outlet).

Note: Since this machine can weigh up to 726

kg, it is essential to check the permissible load

per square meter of the floor.

The machine may only be used for its

intended purpose!

The machine’s mains connection must

be freely accessible!

The machine should only be operated

in closed rooms within a temperature

range of 10 to 40° C!

NUMBERED PARTS:

15 = Feed table (fig. 1)

16 = Protective angle, left side (fig. 1)

17 = Protective angle, right side (fig. 1)

18 = Switch flap „Shredder bin full“ (fig. 3)

19 = Levelling screw (fig. 2)

20 = Base frame, left side (fig. 1)

21 = Base frame, right side (fig. 1)

22 = Dividing panel (fig.1)

23 = Shredder bin (fig. 4)

24 = Shredder bin stirrup (fig. 4)

25 = Shredder bin front panel (fig. 4)

INSTALLING THE

BASE FRAMES (Figs. 1 and 2):

1. Remove the dividing panel (22) from between

the two frames (20+21), using the special

purpose spanners provided.

2. Remove both frames (20+21) from the housing

case.

3. Lift the complete unit and rotate the two frames

by 180° so that the open ends of the frame are

facing downwards. Re-attach the frames to the

housing using four screws (M 10x20) and lock

washers.

4. Place the dividing panel (22) beneath the feed

table between the two frames. Attach the plate

to the frames using two screws (M 10x20) and

lock washers.

5. Lower the complete unit and use the plastic

stoppers supplied to seal off the remaining

open holes on the base frame.

Ensure all parts of the base frame

are firmly screwed together before

lowering the shredder!

6. Adjust the levelling screws (19) to compensate

for any unevenness in the floor (fig. 2).

INSTALLING THE FEED TABLE (15) (Fig. 1):

1. Remove the hexagonal nuts and the lock

washers from the 4 projecting screws on the

front panel of the housing.

2. Place the feed table on the conveyor belt so

that the ends of the screws go through the holes

on the feed table. Push the table up against

the housing and attach it to the front panel

using the nuts and washers you have already

removed.

3. To ensure that the feed table is secure, unscrew

the two hexagonal screws under the feed table

as far as possible, and secure each with a

hexagonal nut.

4. Guide the power cable for the emergency-stop

rail (14) through the sleeve on the front side

of the housing, through the cable gland on the

bottom of the switch box, and on into the switch

box. Then connect the blue wire to terminal 20

and the brown wire to terminal 19.

The emergency-stop rail detailed

under point 4 must be installed by

a qualified electrician!

INSTALLING THE

PROTECTIVE ANGLES (Fig. 1):

Secure the two protective angles (16+17) to the

right and left of the feed table (15) using the 6 flat

headed screws.

INSTALLING THE SWITCH FLAP (Fig. 3):

Screw the switch flap (18) to the hinge located

at the outlet (behind the cutter), using the two

available screws, as illustrated.

INSTALLING THE

SHREDDER BIN (23) (Fig. 4):

Only the original shredder bin which

was delivered with the machine may

be used!

The use of other shredder bins is not

permitted because this might allow the

operator to reach into the underside of

the machine and represents a safety

hazard.

Note: The connecting bolts and locking elements

used to connect the back panel, the two side pa-

nels, and the base frame are included in delivery.

Insert the bolt through the panel you wish to connect

and match it to the locking element on the other

part. Turning the locking element clockwise (in the

direction of the arrow) secures the bolt.

To assemble the shredder bin proceed as fol-

lows:

1. Connect the back panel to the base frame.

2. Connect the side panels (lighter shaded side

facing inwards) to the base frame and back

panel.

3. Connect the front panel (25) to the base frame

using the hinge bolts supplied (insert the hinge

bolts into the hinges from the outside).

4. Insert the stirrup hinge bolts through the side

panels, as illustrated. Then, place the ends of

the stirrup (24) through the holes in the hinge

bolts, and finally, secure the stirrup using the

two locking screws.

5. Attach the buffers to the front panel, as illust-

rated.

6. Insert the base plate, bring up the front panel

and secure in place with the stirrup.

7. Now you can place a plastic bag in the bin and

fold the end of the bag over the bin rim.

15.90 S/16.50 S