20. Place the 9201-1-7 (7/32” SS Ball) down inside the 4101-15-1
(Check Valve Body) through the double threaded side.
21. Install the 4101-16-1 (Compression Spring) into the 4101-15-1
(Check Valve Body) onto the top of the 9201-1-7 (7/32” SS Ball).
22. Screw the 4101-17-1 (Spring Retainer) into the inside of the
4101-15-1 (Check Valve Body), Compressing the Spring between
the Retainer and the SS Ball.
23. Place a 7301-9-013 (O-Ring) over the single threaded end of the
4101-15-1 (Check Valve Body), and screw the Check Valve into
the 4101-14-1 (Outlet Body).
24. Place a 7301-97301-9-013 (O-Ring over the double threaded end
of the 4101-15-1 (Check Valve Body) until it is in the thread relief
area between the two set of threads and against the end of the
4101-18-1 (Jam Nut).