2.2 Position of Process Flanges for Launch and Detect Units:

Process flanges should be located on the process such that the Launch and Detect Units can be
installed, accessed removed in a safe and convenient manner.
The following criteria/Check List should be met at a minimum:

Good, Safe Engineering practices

Local codes and regulations for such equipment installation

Appropriate hazardous area (if applicable) precautions

Owner Company best practice and engineering standards

Access for personnel to stand in front of launch and Detect Units

Clearance for installation and removal of Launch and Detect (see below)

Clearance for installation and removal of purge insertion tubes (if applicable)

Access to process isolation valves

Safe routing for interconnecting cables

Ambient conditions in accordance with analyzer limits

Access to appropriate utilities

Adjacent space for mounting to Calibration Cell when off-line