3.3 Process Flange Welding Alignment and Line-Up

The Launch and Detect units are provided with alignment mechanisms that allow for some manual adjustment
of the laser beam direction in both planes. It is however recommended that the following angular tolerances be
adhered to as closely as possible.

PROCESS FLANGE
BOLT ALIGNMENT

NOZZLE FLANGE BOLT PATTERN MUST BE AS
INDICATED TO ASSURE PROPER MOUNTING OF
ANALYZER LAUNCH AND DETECT UNITS

COMBINED ANGULAR OFFSET OF BOTH NOZZLES
MUST NOT EXCEED 2” IN ANY DIRECTION. BEST
INSTALLATION WILL HAVE NO ANGULAR OFFSET

PROCESS FLANGE
ANGULAR TOLERANCE

Angular tolerance

<3 INSTALLATION AND WIRING> 3-4

Figure 5 - Angular Alignment Tolerances for Launch or Detect Unit Flanges

IM 11Y01B02-11E-A 5th Edition :June 5, 2012-00