3.4 Process Flange Clear Aperture

The Launch and Detect unit fl anges (and insertion tubes if used) should be installed in such a way that a
minimum clear through aperture (opening) diameter of 1 ½” (38 mm) when the distance between the 2” 150#
fl ange faces does not exceed 6ft (~2 m).

Note: Larger clear through apertures may be required when operating over longer distances –
CONSULT FACTORY for further details.

3.5 Mounting the Launch and Detect Units to the Process Flange

Securely bolt the Launch and Detect Units to the process fl anges using the standard bolt holes provided. Ensure
the correct size bolts, nuts, and gasket are used in accordance with the fl ange specifi cations and in accordance
with the process specifi cations when applicable.

NOTE: If the process isolation valve fl ange is excessively hot due to the process temperature or radiant
heat, then a thermal insolating fl ange gasket should be used in order to minimize the heat transfer to the
analyzer fl ange face.

It is generally benefi cial to make the fl ange of the Launch and Detect Units and the fl ange of the process
concentric with each other. Due to the large clearance provided by standard fl anges and bolts, it is possible to
mount the two fl anges in an un-concentric manner – this should be avoided to aid laser beam alignment.

Figure 6 - Clear Aperture for Launch or Detect Unit Flanges

PROCESS FLANGE

CLEAR APERTURE TOLERANCE

LATERAL OFFSET OF NOZZELS MUST BE MINIZED AS TO

ALLOW FOR MINMUM 1.75” [45MM] CLEAR APERTURE.

BEST INSTALLATION WILL HAVE NO LATEAL OFFSET.

3-5

<3 INSTALLATION AND WIRING>