4 test procedures, Insulation resistance, Protective grounding – Yokogawa µR20000 User Manual

Page 21: Test procedures -8 insulation resistance -8, Protective grounding -8

Advertising
background image

3-8

SM 04P01B01-01E

3.4

Test Procedures

Insulation Resistance

Procedures

Perform a measurement with an insulation tester and check whether the results meet
the criteria. Perform the measurement with the power switch turned ON.
Criteria

Terminals Measured

Criteria

Condition

Between the power and earth terminals

100 MΩ or more

Short the L and N terminals.

Between the input and earth terminals

100 MΩ or more

Short all input terminals.

Between input terminals

100 MΩ or more

Short the odd and even channels of
the +/A, −/B, and b* terminals, and
measure between odd and even
channels.

Between the relay contact output

100 MΩ or more

With the /A1, /A2, /A3, or /F1

terminals and earth terminals

option. Short all relay contact
output terminals.

Between remote control input

100 MΩ or more

With the /R1 option.

C terminal and earth terminals

Between the RS-422A/485 SG

100 MΩ or more

With the /C3 option.

terminals and earth terminals

Between the Ethernet terminal

100 MΩ or more

With the /C7 option. Short all

and earth terminals.

input/output terminals

*

With the dot model without the /N2 option, exclude the b terminal. The b terminals are
connected to all channels.

Protective Grounding

Procedures

Perform a resistance measurement with a DMM (Digital Multi Meter), and check
whether the results meet the criterion.
Criterion

Measured Location

Criterion

Between earth terminal and power supply heat sink

0.2 Ω or less

Heat sink

Earth terminal