Operation – Operation Procedures

20

Smart-UPS® VT 10-40 kVA 400V, 208V, 200V – Operation

990-2282A-001

Restart – single system with MBP.

Note

Auto-detection on frequency – if a problem occurs call APC Customer Support (see the
back cover of this manual).

Warning

Only trained personnel familiar with the construction and the equipment may

restart the UPS.

From the XR Enclosure(s) (if available):

Connect the batteries by pushing them in.

From the UPS: Connect the batteries by

pushing them in.

From the XR Enclosure(s) (if available): Set

the DC disconnect switch (if available) to the

ON

position.

From the external MBP: Turn the input switch

(Q001)

to position “1”

(ON)

.

From the external MBP: Turn the output

switch

(Q002)

to position “I”

(ON)

.

From the UPS: Turn load

ON

from the display

via Control

Turn Load on

Yes, turn

Load on.

Check that the load is

ON

.

Note

The UPS is now ready to support the load.

Note

Auto-detection on frequency – if a problem occurs call APC Customer Support (see the
back cover of this manual).