Secondary PCI riser cage option
WARNING!
To reduce the risk of personal injury, electric shock, or damage to the equipment,
remove the power cord to remove power from the server. The front panel Power On/Standby button
does not completely shut off system power. Portions of the power supply and some internal circuitry
remain active until AC power is removed.
CAUTION:
To prevent improper cooling and thermal damage, do not operate the server unless all
PCI slots have either an expansion slot cover or an expansion board installed.
IMPORTANT:
The secondary PCI riser cage option requires both processors.
To install the component:
1.
Power down the server on page 18
2.
Remove all power:
a.
Disconnect each power cord from the power source.
b.
Disconnect each power cord from the server.
3.
Extend the server from the rack on page 19
4.
Remove the access panel on page 20
.
5.
Remove the PCI riser blank.