ASSEMBLY AND INSTALLATION INSTRUCTIONS

for Premium Aluminum (A-500) and Premium Atlantic Aluminum Sliding Patio Doors (JII020)

5

PREPARE BUILDING WRAP

(For masonry/block wall
construction, skip to SILL
PANS)
Trim building wrap flush
with the edge of the
rough opening at the
head and sides.

SILL PANS

(For a recessed sill pocket, skip to COMPLETE OPENING PREP)
The sill can be prepared using one of two methods: We recommend
SureSill™ Sloped Sill Pan™ available from SureSill at www.suresill.com,
building supply stores, and some manufacturing locations or fabricate
a sill pan on site. If installing a SureSill™ sill pan, follow SureSill™'s
instructions for installation and skip to section 5 “INSTALL FRAME“. If
fabricating a sill pan on the job site, follow the instructions below.

JOBSITE FABRICATED SILL PAN

(For a recessed
sill pocket, skip
to COMPLETE
OPENING PREP)

Note!

If using self-

adhesive flashing in
place of a metal pan,
the flashing must be a
minimum of 40 mils and
have a proper back dam,
such as a metal angle.
Use primer if adhering
to concrete.
• Cut a piece of sheet

material to the length
shown.

• Lightly crease folding

lines 1/2" in from the
two short sides and
one long side.

• Measure the width

of the exterior edge
of the frame and add
9/16".

• Take this distance from

the back edge of the
sheet material and
lightly crease a folding
line.

• Cut 1/2" in at this line

on both sides of the
sheet material.

• Fold the three back

sides up to make a
3-sided box.

• For step-down

landings, fold the
front flap down. For
continuous slabs, remove the front flap.

INSTALL SILL PAN

Note!

If installing

a metal sill pan on
concrete, the bottom
surface must be covered
with self-adhesive
flashing.
• Set the sill pan in place

pressing it down firmly
into the sealant. Use
a J-roller if necessary
to ensure a smooth,
secure seal.

• Apply a 3/8"

continuous bead of
sealant across the sill
pan back dam.

• For step-down landing

apply a layer of liquid
flashing across the
lower lip of the sill
pan, joining it to the
face of the foundation.

PREPARE ROUGH OPENING

4

Frame

width

+9/16"

Length of rough opening sill plus 1"

1/2"

1/2"

Fold sides and back up

Fold corner

forward

Fold front

flap down

PREPARE SILL

• Set the sill pan in place

and mark a line across
the back of the sill pan
with a pencil as shown.
Remove sill pan.

• Apply three 3/8" beads

of sealant between the
marked line and the
exterior edge of the
rough sill.

Sealant

Sealant

COMPLETE OPENING PREP

Waterproof the rough
opening with one of the
following methods:
• Wrap the buck or stud

completely with self-
adhesive flashing, then
seal the joint between
the flashing and the
structure, and at the
corners as shown.

OR
• Apply liquid applied

flashing in a smooth
1/16" thick layer
covering the exterior
face of the structure
in a 6" width. Apply
1/16" thick layer
to cover the entire
surface of the head and jambs, extending onto the sides of the sill
pan or across the entire surface of the sill pocket.

Liquid

flashing

For continuous

slab, remove flap

Sealant

Self-

adhesive

or liquid

flashing

Self-adhesive

flashing

Sealant

Measure

frame

width